OpenHydro platform decommissioning
European Marine Energy Centre (EMEC) Ltd · £650,000 · closes 4 Mar 2024
£650,000
Estimated value
Closed
Deadline
18 Jan 2024
Published
This tender has closed.
See what's open in community and personal services, or get contracts like this in your inbox each morning — free.
About this contract
Decommission fully the OpenHydro test platform at our tidal test site of Fall of Warnes, Orkney. Removal of platform, disconnection and testing of 11 kV subsea cable.
Key dates
Published18 Jan 2024
Submission deadline4 Mar 2024 Add to calendar ↓
Source
Source notice on Find a TenderView ↗
Lot — bid on it if it fits
This contract has one lot. Bid if it suits your firm.
To decommission fully the OpenHydro test platform at our tidal test site of Fall of Warnes on berth 4, Orkney Islands
Contractor’s scope of work shall include, but is not to be limited, to:
- Preparation of suitable method and risk assessment to conduct the tasks, including necessary visit to the platform.
- Removal of all the top structure including gantry, winches, container
- Removal of the two drilled grouted piles - flush to the seabed
- Disconnection of the 11 kV marine cable attached to the West pile and terminating the cable with a suitable test end provided by EMEC.
- Test the marine cable (test suite provided by EMEC).
- Make the removed top sections of the piles available to EMEC on Hatston quay or agreed alternative for forensic decommissioning purposes.
- Clearance of sea bed site to the level required by Marine Scotland, final video survey of the site, and report detailing the “as left” status.
- Dispose of all the top structure including the container and piles.
- Provide insurance documents.
- Provide H&S documents.
- Provide method statement and cost breakdown for the works.
Full details given in ITTValue not published