Closed
Machine Lay Carriageway Surfacing Contract_2024
Leicestershire County Council · £20,000,000 · closes 9 Feb 2024
£20,000,000
Estimated value
Closed
Deadline
12 Dec 2023
Published
This tender has closed.
See what's open in construction work, or get contracts like this in your inbox each morning — free.
About this contract
The Council is looking to appoint a single suitably experienced tenderer as a ‘Contractor’ under an NEC4 Term Service Short Contract to undertake the replacement of defective carriageway surfacing and associated accommodation works.
Key dates
Published12 Dec 2023
Submission deadline9 Feb 2024 Add to calendar ↓
Source
Source notice on Find a TenderView ↗
Lot — bid on it if it fits
This contract has one lot. Bid if it suits your firm.
The Council is looking to appoint a single suitably experienced tenderer as a ‘Contractor’ under an NEC4 Term Service Short Contract to undertake the replacement of defective carriageway surfacing and associated accommodation works. This includes:
• Mobilisation:
- early contractor involvement
- attendance at monthly progress and finance meetings
- carrying out the role of Principal Contractor in accordance with the Construction (Design and Management) Regulations 2015
- Liaison and co-ordination with the Client
- working in accordance with the Client’s permit scheme
- assessment of the Health and Safety implications and implementation of safe systems of work, plans and appropriate control measures
- provision and maintenance of compound and stores areas
- supervision of works
- on-site welfare facilities for the Contractor's and Client's use
• Traffic Management:
- Design of traffic management layouts
- Advance notification/permit boards
- Road closures and diversions
- Traffic signal controlled lane closures
- Traffic marshals/Gate persons
- No parking signs and/or cones
- Pedestrian barriers
- Safety fencing
• Accommodation Works:
- Repair and/or adjustment of kerbs and channels in short lengths adjacent to surfacing works
- Adjusting levels of ironworks within surfacing works
- Repair of ironworks within surfacing works
• Cold Milling:
- Removal of defective areas of surfacing by cold milling
- Trimming and working around obstructions
- Removal of all loose material
- Disposal or recycling of non-hazardous arisings
- Storage and recycling of tar bound arisings for reuse
• Surfacing:
- Conventional surface, binder, and base courses
- Polymer modified surface, binder, and base course options
- Environmentally advantageous surface, binder, and base courses options
- Foam-mix recycling and re-use of previously cold milled tar bound materials
- Asphalt reinforcement options
- Bond coat
• Road Markings:
- Reinstatement of screed thermoplastic road markings
• General Requirements:
- The Contractor will assume the role of Principle Contractor and the Client will assume the role of Principle Designer under the Construction Design Management Regulations 2015.
- The service may be required during days, nights, or weekends.
- The Contractor is required to conform with the Client’s PPE requirements, or to a higher standard.
- The Client will undertake testing to ensure compliance with the Specification.
- The Client and Contractor are required to co-operate to ensure that works are planned and completed safely and in the most efficient timescales
- The Contractor will be responsible for defects for a period of 12 months from the completion of each Task Order, unless a longer period is agreed
- Rates submitted at tender will be adjusted monthly – i.e. at the first assessment day and thereafter at each subsequent assessment day£20,000,000
Who to contact
Similar open tenders
closes 10 Jul 2026
closes 15 Jul 2026
closes 15 Jul 2026
Contains public sector information licensed under OGL v3.0