The structural works are to extend the life of the pier by at least 25 years. The scope includes undertaking concrete repairs, installing Impressed Current Cathodic Protection (ICCP) system and removal of timber landing stages.
Due to budget constraints, the Council are considering 3 options, these being: -
• Option A: All Concrete Works Only
Concrete works only. No removal of any of the timber landing stages.
• Option B: All Concrete Works and Part Timber Landing Stage Removal
Concrete works and the complete removal of the Northern and Small Boat timber landing stages only.
• Option C: All Concrete Works and All Timber Landing Stage Removal
Concrete works and complete removal of all of the timber landing stages
All works will be covered by a single NEC4 ECC Option A contract (incorporating a Bill of Quantities for concrete repair works).
The Councils preferred option is Option C, if affordable. If this is not achievable, then the Council will consider Option B and if that isn’t affordable then Option A.
Suppliers can bid to any or all of the 3 options.
This contract is split into lots. You can usually bid for just the ones that suit your firm.
The structural works are to extend the life of the pier by at least 25 years. The scope includes undertaking concrete repairs, installing Impressed Current Cathodic Protection (ICCP) system and removal of timber landing stages.
Due to budget constraints, the Council are considering 3 options, these being: -
• Option A: All Concrete Works Only
Concrete works only. No removal of any of the timber landing stages.
• Option B: All Concrete Works and Part Timber Landing Stage Removal
Concrete works and the complete removal of the Northern and Small Boat timber landing stages only.
• Option C: All Concrete Works and All Timber Landing Stage Removal
Concrete works and complete removal of all of the timber landing stages
All works will be covered by a single NEC4 ECC Option A contract (incorporating a Bill of Quantities for concrete repair works).
The Councils preferred option is Option C, if affordable. If this is not achievable, then the Council will consider Option B and if that isn’t affordable then Option A.
Suppliers can bid to any or all of the 3 options Additional information: Please do not contact any officer/team named on this notice or the documentation. All documentation for this opportunity is available on www.supplyingthesouthwest.org.uk . Any expressions of interest must be made through this portal unless otherwise instructed. You will need to register on the site to submit a bid. Registering is free of charge.Value not published
The structural works are to extend the life of the pier by at least 25 years. The scope includes undertaking concrete repairs, installing Impressed Current Cathodic Protection (ICCP) system and removal of timber landing stages.
Due to budget constraints, the Council are considering 3 options, these being: -
• Option A: All Concrete Works Only
Concrete works only. No removal of any of the timber landing stages.
• Option B: All Concrete Works and Part Timber Landing Stage Removal
Concrete works and the complete removal of the Northern and Small Boat timber landing stages only.
• Option C: All Concrete Works and All Timber Landing Stage Removal
Concrete works and complete removal of all of the timber landing stages
All works will be covered by a single NEC4 ECC Option A contract (incorporating a Bill of Quantities for concrete repair works).
The Councils preferred option is Option C, if affordable. If this is not achievable, then the Council will consider Option B and if that isn’t affordable then Option A.
Suppliers can bid to any or all of the 3 options. Additional information: Please do not contact any officer/team named on this notice or the documentation. All documentation for this opportunity is available on www.supplyingthesouthwest.org.uk . Any expressions of interest must be made through this portal unless otherwise instructed. You will need to register on the site to submit a bid. Registering is free of charge.Value not published
The structural works are to extend the life of the pier by at least 25 years. The scope includes undertaking concrete repairs, installing Impressed Current Cathodic Protection (ICCP) system and removal of timber landing stages.
Due to budget constraints, the Council are considering 3 options, these being: -
• Option A: All Concrete Works Only
Concrete works only. No removal of any of the timber landing stages.
• Option B: All Concrete Works and Part Timber Landing Stage Removal
Concrete works and the complete removal of the Northern and Small Boat timber landing stages only.
• Option C: All Concrete Works and All Timber Landing Stage Removal
Concrete works and complete removal of all of the timber landing stages
All works will be covered by a single NEC4 ECC Option A contract (incorporating a Bill of Quantities for concrete repair works).
The Councils preferred option is Option C, if affordable. If this is not achievable, then the Council will consider Option B and if that isn’t affordable then Option A.
Suppliers can bid to any or all of the 3 options.Value not published